Why a Positive NPV Can Still Sink Your Project: What Lenders Look For

NPV tells you whether a project is worth building. It doesn’t tell you whether a lender will fund it.

Praise Uma · 19 November 2026 · 5 min read

Snapshot

01What NPV actually tells you

If someone offered you $1,000 today or $1,000 next year, you’d take it today. Prices rise, so next year’s $1,000 buys less. Money in your hand can be invested to earn a return. And a promise for next year might not be kept. So money today is normally worth more than the same money later.

Finance puts a number on this. Shrinking future money to what it is worth today is called discounting. Net present value (NPV) adds up what all of a project’s future cash is worth today, then subtracts the cost. If the answer is positive, the project is worth doing.

$1,000 next year is worth about $926 today

Calculation, assuming investors need an 8% return.

NPV answers one question: is this project worth building? It says nothing about a second question, the one lenders ask: can the project repay its loan, year by year, with some room to spare? A project can pass the first and struggle with the second. Let’s look at one.

02A project that looks great on paper

(Illustrative numbers, before tax credits.)

Project100 MW solar farm, US
Assumed lifespan25 years (real projects vary)
Cost to build$110M
Running costs$1.8M a year
Sales12 years at $60/MWh under contract, then $40 at market prices
Cash after running costs$12.4M a year, then $7.7M
Planned funding80% bank loan (6.5% interest) and 20% owner’s cash
Loan term12 years, matching the contract (our assumption)

Each source of money (capital) for the solar project above wants a return, and the project has to pay both in proportion. Blending them gives the rate investors need: about 7.6% (in finance, this is called the weighted average cost of capital, or WACC).

The blended cost of funding is 7.6%Illustrative

Bank loan: 80% × 6.5% = 5.2Owner’s cash: 20% × 12% = 2.4 0%2%4%6%8% 5.2 + 2.4 = 7.6% blended
The owner’s cash asks for a higher return than the lender, because it is paid after the lender and takes more risk.

At that 7.6% rate, the NPV is about +$11M. On paper, this project gets a clear yes.

03What the lender looks at

The lender asks a different question: can the project pay its loan every year?

DSCR = cash available for loan payments ÷ loan payments due that year

Think of a household that has $3,000 a month left after living costs and owes $2,000 a month on its mortgage. It has $1.50 for every $1 it owes, a DSCR of 1.5×. In our case, the owner wants to borrow $88M (80%) and repay it in equal yearly payments over 12 years at 6.5% interest. We assume the loan runs for the same 12 years as the contract, the longest a lender would normally allow for this contract, since NREL notes that loans are almost always shorter than the contract. Each year’s repayment, covering interest plus part of the loan itself, comes to about $10.8M (in year 1, about $5.7M is interest and $5.1M pays down the loan). With $12.4M of cash a year, that is a DSCR of 1.15×.

But lenders want a bigger cushion. They set a minimum DSCR, and here it is 1.30× (our assumption). How high it is depends on risk: predictable income from a long contract with a reliable buyer needs less cushion, while income that depends on market prices or the weather needs more. At 1.15×, our project falls short of the minimum.

Cash covers the payment 1.15 times, short of the lender’s 1.30Illustrative

At 1.15× there is very little room for a bad year. The most the lender will allow is about $9.5M a year (12.4 ÷ 1.30).
Enjoying The Shock Report? Get the next edition in your inbox. Subscribe →

04Why the lender lends less than the owner asked for

A $9.5M yearly payment supports a loan of about $78M, not the $88M the owner asked for. The riskier the lender thinks the cash is, the higher its minimum and the less the project can borrow. The owner has to find the difference from its own cash, and if it can’t, the project doesn’t close.

At the lender’s limit, the loan shrinks by $10M and NPV falls to about $7MIllustrative

The owner needs about $10M more of its own cash. That cash is expensive, so the blended rate rises from 7.6% to about 8.1% and NPV falls from about $11M to about $7M.
The more cushion a lender asks for, the less it lends, and the more the project relies on expensive money.

How the minimum has moved in the US. The US National Renewable Energy Laboratory (NREL) reports that US lenders to solar projects wanted a DSCR of 1.4 in 2010 and 1.3 by 2017. NREL attributes the easier terms partly to solar becoming a more proven technology with fewer risks for lenders, alongside a recovering financial sector. Our 1.30× assumption sits at that 2017 level. Its model of a solar project without tax credits shows what risk does to borrowing:

The riskier the cash looks, the less a project can borrowNREL model

Share of project cost that could be borrowed. Source: NREL (2018), 2017 data, no tax credits.

05A second gap: the years after the loan

The first gap was the cushion. The second is time. NPV counts every year of the project’s life. In our case above, we assumed a 25-year life, so it includes years 13–25, after the contract ends. But the loan is scheduled to be repaid within the 12 contracted years, so the lender sizes it mostly on those years.

About a fifth of the project’s value comes after the loan is repaidIllustrative

Years 1–12 · about 80% of value13–25 · ~20% Contract years: the loan is scheduled to be repaid hereAfter the contract NPV counts both parts. The lender sizes the loan mostly on the first.

And as we saw in the last edition, if market prices fall as more renewables connect, those later years are worth less still, which lowers NPV further, and the owners carry that risk after the lenders are repaid.

NPV asks: is this project worth doing? DSCR asks: can it pay this year, and how much can it borrow? A project has to pass both.

06What owners can do

  1. Longer or stronger contractA contract fixes the price the project is paid for its power. The longer it runs, the more years the lender can count on, so it can lend more. A reliable buyer helps too, because the lender worries less about being paid.An 18-year contract at the same price, not 12: the same $9.5M yearly payment supports about $100M
  2. More owner cash, or a cheaper loanThe lender only lends what the cash can cover, so the owner can fill the gap with more of its own cash (here about $10M). Or the loan can cost less: lower interest means smaller payments, so the same cash supports a bigger loan.At 5.5% instead of 6.5%, the same $9.5M a year supports about $82M
  3. Repayments that flexReal projects’ cash moves around from year to year, so instead of equal payments the loan can follow it: smaller payments in weaker years, bigger ones in stronger years. The lender keeps its cushion every year, and the project is less likely to be caught short.Keeps the cushion even in a bad year
  4. A cash reserveCash is set aside in a separate account. If a year’s income falls short, it pays the lender, so the project doesn’t miss a payment. A reserve typically covers about six months of payments.For our project, about $4.8M

However, each of these options has a downside: longer contracts often mean a lower price, and putting in more cash or holding a reserve ties up money. None removes the risk, but each makes it easier to see before the money is committed.

Is your project bankable?

Our solar farm had a positive NPV and still fell short of the lenders’ 1.30×. A good idea can fail if nobody tests the numbers the way lenders will.

At The Deal Case, we put your team in that seat. In our Energy Investment Simulation, your people build the financial model, take a market shock they didn’t see coming, and defend their decision in front of experienced investors. They get it wrong in the room, not in the market, and they leave knowing how lenders think.

It’s built for corporate teams, in plain language, so engineers, commercial and finance colleagues learn it together.

If you want your team to walk into the next funding conversation ready, email us and let’s talk.

Talk to The Deal Case
Get The Shock Report in your inbox
New editions on energy investment, delivered when they publish.
By subscribing you agree to our privacy policy. Unsubscribe at any time.
Sources